Wednesday, 4 November 2026

£20.4 MILLION FOR WEDNESBURY — MARKET SITE HEADING FOR DISPOSAL, PROJECTS DELAYED AND THE BOARD PREPARING TO CLOSE!

 



SANDWELL INSIGHT: £20.4 MILLION FOR WEDNESBURY — MARKET SITE HEADING FOR DISPOSAL, PROJECTS DELAYED AND THE BOARD PREPARING TO CLOSE!

Public money, market management, disappearing lights, delayed regeneration and a partnership preparing to close before the biggest project is delivered!

Here we go again!

Another Sandwell Council agenda pack, another collection of progress reports, financial figures, positive headlines and assurances about regeneration.

But look a little deeper into the 102-page agenda pack for the Wednesbury Levelling Up Partnership Board meeting scheduled for 12 November 2026, together with the minutes from July, and some very serious questions begin to emerge.

We are talking about £20.4 MILLION of public investment intended to improve Wednesbury.

Not pocket money.

Not loose change.

£20.4 MILLION!

And what do we discover?

The former Wednesbury Outdoor Market site is being prepared for disposal.

A major regeneration project has slipped towards 2030.

A solar lighting scheme has suffered repeated thefts, with the proposed replacement covering fewer locations.

Community engagement actions remain outstanding.

And the partnership board overseeing this investment is already preparing to close.

Oh, and did I mention?

THE PUBLIC AND PRESS ARE NOT ALLOWED INTO THE BOARD MEETINGS!

Apparently, publishing an agenda is considered sufficient transparency.

Well, I don't think so.

£20.4 MILLION — WHERE HAS THE MONEY GONE AND WHAT HAVE WE ACTUALLY ACHIEVED?

The Wednesbury Levelling Up Partnership programme has received its full allocation of £20.4 million, comprising £20.05 million capital and £350,000 revenue.

There have been improvements, and I have no intention of ignoring them.

The Friar Park Millennium Centre has benefited from investment, public realm improvements have taken place, community safety initiatives have progressed, and work is continuing on the Hydes Road pavilion.

All welcome.

But receiving funding, spending funding and delivering lasting improvements are three very different things.

The July Board minutes recorded capital expenditure of £6.68 million at the end of 2025/26, with further expenditure forecast.

Meanwhile, the Friar Park Urban Village element is now forecast to continue across several more financial years.

So where is the clear, accessible, project-by-project financial account showing residents:

  • What has been spent?

  • What has been delivered?

  • What remains outstanding?

  • What has been committed but not yet spent?

  • What are the expected final costs?

  • What measurable benefits have residents actually received?

Not another glossy newsletter.

Not another photograph of somebody cutting a ribbon.

A proper account of public money and public outcomes.

Surely that isn't too much to ask?

WEDNESBURY OUTDOOR MARKET — PUBLIC MONEY SPENT, MARKET MOVED, SITE REMEDIATED... AND NOW THE LAND IS TO BE SOLD?

NOW THIS DESERVES SOME SERIOUS ATTENTION!

Buried within the July Levelling Up Partnership Board minutes is confirmation that remediation of the former Wednesbury Outdoor Market site has been completed and that the site is intended to be marketed for disposal, subject to the town centre masterplan.

YES, DISPOSAL!

Now, before anybody starts celebrating another regeneration opportunity, perhaps we should examine the history of this market, the decisions taken and the public money involved.

Wednesbury's outdoor market was relocated to Market Place and the upper end of Union Street in April 2023.

The relocation has been controversial, with concerns about trader numbers, trading conditions, footfall, accessibility and the suitability of the replacement location.

Questions have also been raised about whether the relocation achieved its intended objectives.

Meanwhile, the former market site has undergone remediation, including work associated with historic shallow mine workings, to prepare it for potential future development.

And now the site is being prepared for marketing and disposal.

STOP RIGHT THERE!

Before any disposal proceeds, I believe residents deserve a complete financial and operational history.

HOW MUCH HAS THIS MARKET ACTUALLY COST THE TAXPAYER?

Let's start with the obvious questions.

How much public money was spent on the original outdoor market facilities?

How much was subsequently spent on maintenance, improvements and associated infrastructure?

What was the total cost of relocating the market?

What expenditure was incurred on the new trading arrangements, utilities, signage and other facilities?

What was the final cost of remediating the former market site?

And which funding streams were used?

Was it council capital funding?

Levelling Up money?

Other government grants?

Or a combination?

Were any of those funds subject to conditions governing the future use, ownership or disposal of the site?

And if the land is now to be sold, what happens to the proceeds?

Will they be reinvested in Wednesbury?

Will they return to the council's wider capital programme?

Could any grant conditions affect the use of those receipts?

What independent valuation has been undertaken?

Will the site be sold freehold, leased or transferred through another arrangement?

And what safeguards will ensure the disposal represents proper value for money?

These are not minor administrative details.

We are talking about public land, public investment and a town centre that desperately needs sustainable regeneration.

I am not suggesting that selling the site is automatically wrong.

There may be a perfectly reasonable case for bringing the land back into productive use.

But that case should be made openly, with the financial evidence available for public scrutiny.

AND WHAT ABOUT THE MARKET MANAGER?

There is another aspect of this story that deserves proper examination.

The role of Sandwell Council's market management.

Who was responsible for providing operational advice on the relocation?

What involvement did the Market Manager have in assessing the suitability of the new location?

Were trader concerns formally recorded?

Were warnings about reduced footfall, declining occupancy or trading viability escalated to senior officers and councillors?

What recommendations were made before the relocation?

What advice was given afterwards when concerns emerged?

Were regular reports produced showing trader numbers, income, expenditure, vacancies and market performance?

And what involvement, if any, has market management had in discussions about the future of the former site?

Let me be clear.

These are questions about professional responsibilities, management advice, operational decisions and accountability.

They are not allegations of personal wrongdoing.

But if decisions were taken on the basis of professional advice, residents should be able to see what that advice was and whether the expected outcomes were achieved.

It is simply not good enough to examine the former market site as an isolated regeneration opportunity while ignoring the wider history of the market itself.

FREE MARKET PITCHES AND PARKING — BUT WHERE IS THE RECOVERY PLAN?

The council has introduced a pilot involving free market pitches and limited free parking at Wednesbury and Great Bridge.

That may help traders, and I hope it does.

But free pitches are not a complete market recovery strategy.

What was the financial position before relocation?

What is it now?

How many traders operated at the old site?

How many operate at the replacement location?

What has happened to market income?

What are the annual operating costs?

How much subsidy is required?

And what measurable improvement is expected from the pilot?

Without that information, how can residents judge whether the council is addressing the underlying problems?

Wednesbury needs a successful, sustainable market.

Not another temporary initiative accompanied by a press release.

BEFORE THE SITE IS DISPOSED OF, SHOW US THE FULL PICTURE!

I want to see a complete chronology of the market decisions, supported by the business cases, financial records, consultation responses, management advice, funding agreements, remediation costs and disposal proposals.

Because the question is not simply what the former market site might be worth today.

It is what the whole sequence of decisions has cost, what it has delivered and whether the people of Wednesbury have received value for money.

PUBLIC MONEY SPENT.

MARKET RELOCATED.

FORMER SITE REMEDIATED.

LAND PREPARED FOR DISPOSAL.

Surely that warrants a full public explanation before the next chapter begins?

THE GREAT SOLAR LIGHTING DISAPPEARING ACT!

Now this really caught my attention.

Solar lighting was installed at several green spaces across Wednesbury as part of the Levelling Up programme.

Unfortunately, lights were stolen.

Replacement lights using a supposedly more secure specification were installed.

And further thefts occurred.

The council now considers repeating the same approach unsuitable.

Fair enough.

But the proposed solution is revealing.

The Board is being asked to approve £52,800 for permanent lighting at Brunswick Park, while changing the locally agreed output from four locations with solar lighting to ONE location with permanent lighting.

FOUR LOCATIONS DOWN TO ONE!

The proposed installation also carries estimated annual electricity and maintenance costs of £1,500.

Now, I support robust lighting where it genuinely improves public safety.

But how much did the original lighting cost?

How much was spent replacing it?

What did removal and making the sites safe cost?

Was theft and vandalism properly considered before installation?

What happens to the other three locations?

And were residents and park users consulted about the proposed change?

The report also identifies other improvements at Brunswick Park being developed through the Pride in Place Impact Fund.

That makes it particularly important to distinguish the funding streams and explain precisely which programme is paying for what.

A failed installation should produce a proper lessons-learned account, not simply another spending proposal.

FRIAR PARK URBAN VILLAGE — FROM 2028 TO 2030!

Here is perhaps the biggest delivery concern in the entire agenda.

The Board is being asked to endorse a change to the Friar Park Urban Village remediation completion date.

Previously: December 2028.

Now: December 2030.

TWO YEARS LATER!

The revised timetable does not anticipate remediation works beginning on site until August 2028.

The report attributes the delay to preparations for the remediation planning application taking longer than expected, affecting subsequent milestones.

This is a complex project involving contaminated land, environmental permissions, planning requirements and a major proposed housing development.

Nobody should underestimate those challenges.

But neither should complexity become an excuse for avoiding difficult questions.

What are the financial implications?

What happens if further delays occur?

What safeguards are in place?

Who carries the additional financial risks?

And how will residents be kept properly informed?

We have already raised numerous questions about Friar Park Urban Village, including matters involving Sandwell Council, the West Midlands Combined Authority and Antonia Bance MP.

Those issues deserve their own detailed investigation, which we will continue separately.

However, one point in this agenda cannot be ignored.

THE BOARD COULD BE GONE BEFORE REMEDIATION EVEN STARTS!

Think about that.

A partnership board overseeing a multimillion-pound programme could be wound up before one of its largest and most complicated projects reaches the construction stage.

Who takes over?

Who scrutinises the expenditure?

Who monitors the risks?

And who answers to residents when problems arise?

THE BOARD IS PREPARING TO CLOSE — BUT THE WORK ISN'T FINISHED!

The November agenda outlines plans to conclude the Wednesbury Levelling Up Partnership Board's governance arrangements during 2027.

A programme closure and evaluation report is anticipated in June, followed by a Cabinet report in July.

The council says most projects should be completed by spring 2027.

But Friar Park Urban Village is clearly going to continue well beyond that.

The report acknowledges that Board members have expressed interest in continuing a formal advisory arrangement, but resources have not been identified to support one.

So what happens?

Does the Board simply disappear?

Will its reporting arrangements disappear with it?

Will residents lose an established route for questioning progress?

I am not suggesting that a Board should continue indefinitely.

But surely proper successor arrangements should be agreed BEFORE the existing governance structure is closed?

And why is an independent evaluation only being considered if revenue underspend can be made available?

For £20.4 million of public investment, an independent evaluation should be an essential part of demonstrating value for money.

Not an optional extra if there happens to be a little money left over.

KALLIANNE TITLEY, BOARD MEMBERSHIP AND THOSE CLOSED DOORS

The published membership lists Kallianne Titley as Chair and Caitlin Terrett as Vice-Chair, alongside councillors, Antonia Bance MP and representatives of other organisations.

I have repeatedly raised concerns about transparency, representation and accountability within community boards and partnership arrangements across Sandwell.

Those concerns remain.

How were members selected?

What criteria were used?

Were opportunities to participate advertised openly?

How were community organisations and residents represented?

Are declarations of interest publicly accessible and regularly updated?

How is political balance addressed?

And why should a partnership overseeing £20.4 million of public investment meet without public or press access?

These are governance questions, not accusations against individual members.

The Board was established in December 2023, when Labour controlled Sandwell Council.

Reform took control in May 2026.

So let's be fair about political responsibility.

The previous Labour administration established the arrangements.

The current Reform administration is responsible for overseeing the programme now, addressing outstanding concerns and ensuring proper accountability.

Changing the political administration should provide an opportunity to examine inherited governance arrangements, not simply continue them without question.

FRIAR PARK MILLENNIUM CENTRE — GOOD NEWS, BUT LET'S SEE THE LONG-TERM RESULTS

The Millennium Centre improvements reached practical completion in June 2026, with an official opening in July.

The Board was told about improved facilities, learning opportunities, NHS-related services and a youth club reportedly attended by approximately 150 children.

That is encouraging.

The Centre is an important community asset, and investment in it should be welcomed.

But completed building works are not the same as demonstrated long-term community benefit.

How many additional residents are accessing training?

How many qualifications have been achieved?

What employment opportunities have resulted?

What are the ongoing running costs?

Who maintains the publicly funded improvements?

And how is fair access to the facilities assured?

These are perfectly reasonable questions.

A successful opening ceremony should be the beginning of measuring community outcomes, not the end of accountability.

WEDNESBURY TOWN CENTRE — WHERE ARE THE MEASURABLE RESULTS?

The July minutes contain some interesting comments from Board members themselves.

Concerns were raised about vacant shops, absentee property owners, parking, accessibility and whether the Wednesbury Masterplan was achieving its objectives.

These are issues residents and traders have been raising for years.

Shopfront improvements have taken place.

Public realm projects have progressed.

Development opportunities are being considered.

But the November agenda proposes another verbal update on key town centre sites.

A VERBAL UPDATE!

Where is the comprehensive written report?

Where are the figures for empty premises, new businesses, footfall, investment and accessibility?

What has actually changed for struggling traders?

What improvements can disabled residents see?

And how much of the investment is creating lasting economic activity?

Wednesbury needs a thriving town centre.

Not just a collection of completed project milestones.

COMMUNITY ENGAGEMENT — STILL WAITING, STILL PROMISING!

The communication action logs are another interesting read.

Some actions concerning Friar Park Urban Village date back to July 2025.

They include public information materials, a remediation video, communication with young people, community display locations and engagement with Wednesbury Action Group.

By November 2026, several matters were still awaiting completion, review or action linked to the planning application.

The council records offers to meet Wednesbury Action Group, and its log also records a previously arranged meeting being cancelled by a group member.

That is the council's recorded position.

But the wider issue remains.

Residents need timely information and genuine opportunities to ask questions.

Not simply carefully prepared announcements once plans are well advanced.

The council has also indicated that a proposed remediation drop-in event would not proceed during the planning application phase because of its role as planning authority.

Maintaining planning impartiality is important.

But that does not remove the need to provide factual information about environmental risks, remediation and project delivery.

COMMUNICATION IS NOT CONSULTATION.

And consultation is not meaningful if difficult questions remain unanswered.

TEN QUESTIONS SANDWELL COUNCIL SHOULD ANSWER

Before this Board is wound up, I believe the council should answer the following:

  1. What is the full financial history of Wednesbury Outdoor Market, including its relocation, infrastructure, operational costs and former-site remediation?

  2. What advice did market management provide before and after relocation, and what evidence was used to assess the consequences for traders?

  3. What are the proposed terms of disposal of the former market site, what is its independently assessed value, and how will any capital receipt be used?

  4. How much of the £20.4 million Levelling Up allocation has actually been spent, committed and delivered against the original objectives?

  5. What were the total costs of the failed solar lighting installations, replacements and removal, and why is the proposed replacement now limited to one location?

  6. What measurable long-term benefits have resulted from investment in the Millennium Centre, town centre and public spaces?

  7. Why has Friar Park Urban Village remediation slipped to December 2030, and what are the consequences for funding, risks and future delivery?

  8. Who will scrutinise the outstanding projects once the Levelling Up Partnership Board closes?

  9. Will the council commission an independent evaluation and publish the complete findings?

  10. Will the council review the transparency of Board membership, declarations of interest, public access and future community representation?

These are not unreasonable demands.

They are the questions that should accompany substantial public expenditure.

MY FINAL THOUGHTS — DON'T CLOSE THE BOOK WHILE THE STORY IS STILL UNFINISHED!

There have been worthwhile improvements under the Wednesbury Levelling Up Partnership.

Let's recognise them.

But let's not confuse spending with success, activity with achievement, or preparing a site for disposal with delivering regeneration.

The former Outdoor Market site raises particularly important questions.

How much public money has been spent across the history of the market?

What happened to the original objectives?

What advice was given?

What have traders gained or lost?

And what will residents receive if the former site is disposed of?

These questions deserve answers before the council moves on.

Meanwhile, Friar Park Urban Village is slipping towards 2030, lighting proposals have been reduced in scope, and the Board is already discussing its own closure.

The people of Wednesbury deserve to know what has been achieved, what has gone wrong, what remains unfinished and who will be accountable.

Because £20.4 million deserves rather more than a farewell meeting, a lessons-learned report and a pat on the back.

And before anybody closes the Board, perhaps they should answer one final question.

IF THE MONEY HAS BEEN ALLOCATED, THE MARKET SITE IS BEING PREPARED FOR DISPOSAL, THE BIGGEST PROJECT IS STILL YEARS AWAY FROM COMPLETION AND THE BOARD IS ABOUT TO DISAPPEAR...

WHO, EXACTLY, IS ANSWERING TO THE PEOPLE OF WEDNESBURY?

We look forward to the answers.


#SandwellInsight #SandwellCouncil #Wednesbury #WednesburyMarket #MarketRelocation #PublicLand #LevellingUp #PublicMoney #Accountability #Transparency #FriarPark #FriarParkUrbanVillage #MillenniumCentre #BrunswickPark #HydesRoad #WednesburyTownCentre #CommunityEngagement #LocalDemocracy #SandwellPolitics #ValueForMoney



No comments: